Attached to Chelsea’s world famous Stamford Bridge football ground, this hotel is certainly in the premier league – and maintains its position by always welcoming visitors with an impressive display.
 
So when our Romford-based team arrived, they knew they would have to put on a winning performance. The task facing them was the soft refurbishment of 76 bedrooms, which required a fully professional approach in all areas and special attention to all the finishing touches.
 
This included expert French polishing, stripping ceilings of Artex and replastering, and redecorating the walls with wide vinyl Muraspec. New lighting was fitted and all en-suite bathrooms were given new showers and taps. The rooms were tastefully fitted out with new furniture and artwork to complete the stunning result.
 
All works were carried out over 3 phases, each lasting 3 weeks. To reduce impact on the hotel’s revenue, each phase had to be completed and handed back to a strict time schedule so that the next phase was available. In fact, we actually improved our system of works to such an extent that we managed to hand back half of Phase 3 two weeks earlier than programme -  enabling the hotel to gain revenue for these rooms.
 
As the hotel forms part of the Chelsea football ground complex, we also had to make sure that deliveries didn’t clash with the Club’s afternoon or evening fixtures. Every obstacle was overcome, the contract was completed on time and to budget . . . and the hotel got the goals they wanted.